Pickstone-Peerless gold production up 28pct in Q4
By Respect Gwenzi, Feb 02, 2018
AIM listed junior miner Vast Resources said gold production at its Pickstone-Peerless mine in Chegutu increased by 28 percent to 6,057 ounces in the fourth quarter ending December 2017 compared to 4,738 ounces recorded in September.
In a quarterly production summary, the group said 90,874 tonnes of ore were mined, a 27 percent increase from the 71,533 tonnes recorded in the previous quarter.
The group said production of sulphide ore is scheduled to start this year and a significant increase in installed primary milling capacity is anticipated once the sulphide plant is commissioned to 33,000 tonnes per month.
“Construction of the sulphide plant is progressing – crushing, milling and leaching components of plant now commissioned and flotation cells to be commissioned in the coming months,” said chief executive Andrew Prelea.
“Mill grade is expected to increase from 2.33g/t to between 3.00g/t and 4.00g/t over a six to nine month period as higher grade sulphide ore is mined and processed, resulting in a significant increase in production.”
The company said evaluation of the Giant Gold Project was ongoing and that artisanal miners had been relocated from the licensed area.-Source
Top Stories
South Africa’s Maize Export Market Faces Pressure as Zimbabwe Moves From Deficit to Surplus
Zimbabwe, once the bread-basket of Africa has accounted for 38% of South Africa's maize exports in the 2025-26 marketing year, absorbing approximately 741,000 metric tonnes out of a total of 1.95 mill
1 day agoBeyond the Agreements: Why Plumtree Has Become the Credibility Test of the Zimbabwe–Botswana BNC
Zimbabwe and Botswana have concluded the Fifth Session of their Bi-National Commission in Harare on 22 April 2026, with President Emmerson Mnangagwa and Botswana President Advocate Duma Gideon Boko co
Apr 23, 2026
